As of November 23, 2026, Ethereum’s planned Glamsterdam upgrade had no activation date for the Hoodi testnet or mainnet. The unresolved question is whether proposed gas-pricing changes in EIP-8037 and EIP-8038 would disrupt contracts already deployed on Ethereum. An analysis cited in the original reporting estimated that about 200,000 deployed contracts could be affected; that is not a count of contracts confirmed to have failed.
Where the upgrade stands
Glamsterdam activated on Sepolia on October 6. At the October 22 ACDE #248 meeting, developers postponed its planned October 26 Hoodi activation so they could investigate how EIP-8037 interacts with mainnet contracts. A concurrent plan to raise Hoodi’s block gas limit to 200 million was also cancelled. On November 6, the Ethereum Foundation said Hoodi would not fork until the issues were resolved.
Hoodi was intended as a further test before setting a mainnet date. Glamsterdam had previously targeted the fourth quarter of 2026, but no mainnet activation date had been set by the reporting date. The disputed rules had not activated on mainnet, so the reported compatibility risk was not yet a change affecting mainnet users.

The compatibility problem
EIP-8037 would raise the gas charged for opening a new storage slot to roughly five times its previous level. Its purpose is to price persistent storage more closely to the burden it places on nodes as block gas limits rise. Existing contracts can, however, assume a particular gas cost or use remaining gas to decide what to do next. A higher charge could cause some of those operations to fail or behave differently.
An Ethereum Foundation assessment on August 24 replayed historical mainnet transactions and initially found only a small number of affected contracts, many of which could be fixed by increasing gas limits. The foundation subsequently reviewed the issue with ChainSecurity and Dedaub; the later analysis cited in the report put the potentially affected deployed-contract count at about 200,000.

Decisions still open
Ahead of the November 19 ACDE #249 meeting, the Besu team set out two paths, both involving a delay: revise EIP-8037, or remove it from Glamsterdam and consider it for the subsequent Hegotá upgrade. Besu favored revision and warned against deploying a change that breaks existing contracts. It said removal would require renewed checks of dependent features and would weaken BAL, a feature intended to improve node-processing efficiency. Besu also said its proposed paths would mean giving up Sepolia as a testnet for the revised upgrade.
The Geth team challenged that framing. It said proceeding with the existing specification remained a third option, and argued that revising EIP-8037 would save only a minority of affected contracts because many have gas assumptions hard-coded. Besu responded that failures caused by hard-coded gas costs were acceptable to it, but broken try/catch fallback behavior or new problems arising from a higher gas limit were not.
External reports cited in the original article offered conditional mainnet estimates ranging from mid-January 2027, if the rules stayed unchanged, to April–May 2027 if they were revised. None was an agreed activation schedule.
Developer Leo Glisic has proposed the draft EIP-8488 as another approach: retain the old gas rules for contracts deployed before the upgrade and apply new, higher-priced V2 instructions to newly deployed contracts. Giulio Rebuffo has submitted a competing compatibility proposal. EIP-8488 remained under discussion and had not entered the developers’ formal meeting agenda.
The uncertainty has also reached applications. 1inch told users participating in resolver delegated staking to claim 1INCH rewards and undelegate by November 27, warning that rewards could otherwise be lost. 1inch attributed its warning to the proposed Glamsterdam gas rules making the relevant contracts unsafe to use. The Ethereum Foundation, ChainSecurity and Dedaub had together contacted at least 50 affected companies; three projects were classified as high-impact, with fixes completed or expected by mid-December. Developers said preparations for Hegotá, planned for 2027, were continuing despite Glamsterdam’s delay.